- Uganda Karuma Hydropower Station
- time:2026-01-23 17:13:56

Basic Information
- Location: On the Kaduna River in Zanggeru Town, Niger State, Nigeria, over 200 km from the capital Abuja.
- Project Positioning: Largest hydropower station in Nigeria (under construction/completed); key project under the Belt and Road Initiative in Africa.
- Total Installed Capacity: 700 MW (4 x 175 MW vertical Francis turbine-generator units).
- Annual Average Generation: 2.64 billion kWh.
- Power Supply Capacity: Sufficient to meet the electricity demand of two cities the size of Abuja.
-
Sales quantity: 9 sets of grouting recorders, equipped with flow meters, pressure gauges, density meters, heave observation devices, data logging systems, and data processing software
Construction Timeline
- May 2013: Awarded to PowerChina as EPC contractor (contract value: USD 1.294 billion).
- April 28, 2021: Reservoir impoundment completed (overcoming local community disruptions and pandemic challenges).
- March 28, 2022: First unit commissioned.
- September 26, 2022: Second unit stator installation completed.
- December 28, 2022: All four units operational.
- May 25, 2023: Full-load grid connection and 25% load rejection tests successfully completed.
- June 2023: All units grid-connected and ready for commercial operation.
- August 14, 2023: Official handover certificate issued by client, entering warranty period.
Engineering and Technical Features
- Dam Type: Roller Compacted Concrete (RCC) Gravity Dam.
- RCC Volume: Over 2 million m³.
- Peak Construction Intensity: 135,000 m³/month.
- Construction Method: Direct discharge by dump trucks, motor grader paving, vibratory roller compaction.
- Key Advantages: Simplified construction, reduced cementitious material usage, and lower costs.
Investment and Contractors
- Funding: "Two Preferential Loans" from China Eximbank.
- Contract Value: USD 1.294 billion.
- EPC Consortium:
- PowerChina (67.5% equity)
- Sinohydro Corporation (32.5% equity)
- Construction Units:
- PowerChina's 83 Joint Venture (8th and 3rd Bureau)
- Design Institute: PowerChina Kunming Engineering Corporation.
Comprehensive Benefits
-
Power Generation:
- Annual generation: 2.64 billion kWh.
- Meets demand for two Abuja-sized cities.
- Alleviates Nigeria's chronic power shortages.
-
Socio-Economic Benefits:
- Employed over 5,000 local workers at peak.
- Created over 4,000 jobs during construction.
- Provided free medical facilities to local communities.
- Improved security through large-scale employment.
-
Environmental Benefits:
- Reduces CO₂ emissions by 400,000 tons/year.
- Promotes Nigeria's energy structure optimization and green development.
-
Multi-Functionality: Combines power generation with flood control, irrigation, water supply, aquaculture, and navigation.
Project Significance and Honors
-
Strategic Importance: China Eximbank's largest power financing project in Nigeria.
-
Sino-African Cooperation: Exemplary Belt and Road project in Africa.
-
Awards:
- February 6, 2023: Honored as one of Hunan Province's "Top 10 Sino-African Trade Projects."
- Praised by H.E. Garba Sani, Niger's Ambassador to China, as an infrastructure benchmark for Africa.
-
International Impact: Provides a foundation for resolving Nigeria's energy shortages and improving power supply.
Challenges and Solutions
- Key Challenges: Local community disruptions and pandemic constraints.
- Mitigation Measures:
- Strict compliance with Nigerian regulations and pandemic protocols.
- PowerChina completed civil works ahead of schedule by mid-December 2021.
- Team ensured stable unit operations and passed all tests on first attempt.
The Zanggeru Hydropower Station, Nigeria's largest, exemplifies Sino-African cooperation. It addresses energy shortages, creates jobs, stimulates economic growth, and promotes environmental protection, serving as a model for Belt and Road Initiative implementation in Africa.




